Spot on—otherwise a 10mm drift in the cavity leaf forces the joiners to scribe factory-milled door linings on site just to keep the corridor runs flush.
Spot on—pointing out that tolerance gap between standard block modules and studwork is the kind of site reality way too many set-out drawings ignore. Structural grid lines are the only true neutral ground once trades start overlapping.
Grid lines are sacred for a reason. Watching tolerance stack-up eat through a 15mm movement joint on site is a rite of passage nobody wants.
Had a site team here in UAQ try dimensioning three floors of drywall off a hand-laid block wall instead of Grid C. We ended up with a corridor that tapered by 90 millimetres and a fire door that refused to fit its opening.
Spot on. The second you tie drywall to a masonry face, a 15mm blockwork drift compounds down the line until your pre-ordered door jambs suddenly don't fit the rough openings.